Radiomovel Network Operation Center, Sintra Portugal

Project Management of the new Head Office building for the Radiomovel operator of data high speed data communications. Implanted in 6.700 m2 terrain, include 1.100 m2 of offices,  the NOC (Network Operate Center), a Data Center with 600 m2 and Technical Facilities and Warehouse with 1.300 m2.

Cost of the project 16 M€. The Project Management included Design Control, Site Inspection, Quality control, Planning and Cost Control.

Civil Works, Electricity, Telecom, UPS & Generator, Fire & Smoke Detection, Fire Fighting Systems, Precision Air Air Conditioning, Water & Sewer

Radiomovel Data Center, Sintra Portugal

Responsible for the Project Management of a Data Center with 600 m2 and Technical Facilities and Warehouse with 1.300 m2 in the the new Head Office building of Radiomovel operator of data high speed data communications and Internet services, voice over Internet services, virtual privative networks services, and trunking services.

The Project Management included Design Control, Site Inspection, Quality control, Planning and Cost Control.

Civil Works, Electricity, Telecom, UPS & Generator, Fire & Smoke Detection, Fire Fighting Systems, Precision Air Air Conditioning, Water & Sewer

Radiomovel GreenField Sites, FDS - Fast Deploiment Solution

After a challenge of our client to make a GreenField Site in a delay that cannot be stop by administrative procedures, we put our engineering department searching for structural design solution to speed up all the construction process.

After this, PROCONSULTORES developed the FDS (Fast Deployment Solution) that allows a GreenField Site on air, with towers up to 50m high, in 3 days from ground zero. This solution as a Patent Pending of PROCONSULTORES company.

We implement several GreenField Sites for the CDMA network for Radiomovel in Portugal.

Orascom / Djezzy GreenField Sites, FDS - Fast Deploiment Solution

In Algeria we build for Djezzy, the first Algerian Telecom Operator, a FDS GreenField site that is on air since 2006.

This first experience in Algeria took us 5 days to conclude it, with local staff.

THALES - Telecom GSMR & Optical Fiber supervision 150 Km railway

Supervision of installation of Telecom systems on the 150 Km railway line Barika (Ain Touta to M'Sila) , Algeria, includind GSM-R, SDH, Fiber Optics, Management Telephony, Security Telephony, Clocks, PAS, PIS and Data Network.

Work progress supervision, optical fiber launch and optical fiber test supervision, verification of the tests carried out on the various subsystems and the conformity of the installation with the engineering plans.

Collection of information leading to the execution of the registration of the different subsystems.

THALES - Telecom Site Survey in Barika railway

Site Survey of the technical rooms in 7 railway stations, in the Barika railway line.

Collection of information leading to the execution of the registration of the different subsystems.

trabalhador da construção
1509440462project_1508849662project_4.jp
estação de trem
a923ce252ca0c68824cea9b892b844a8.jpg

HUAWEI / MOBILIS  -  Data Center of Boussada

Site Survey and Design in BIM of the technical rooms and Building Facilities. 

Coordination of different infrastructures like cable tray, medium and low voltage, fiber optics, fire alarm, intrusion alarm, acces control, CCTV, humidity alarm, ventilation, AC and DC voltage with equipment installation and construction details.

Design of Dynamic 3D Viewing in BIMx for better site work implementation, coordination and control.

Task Planning and Quality Control.

As Build Drawings and Documents.

51.jpg
18.jpg
29.jpg
1548260488468.jpg
1548260488838.jpg

ZTE / ALGÉRIE TELECOM  -  FTTX à Guelma

FTTX projet in Guelma mainly related to ODN work

Work carried out on 02 different zones consisting in 9 sites including the fitting out of optical equipment and accessories of 02 OLT.
Connection of more than 64 fiber optic buildings from end to end (FDT - FAT link).
Installation of more than 15,260 meters of optical fiber.
Supply and installation of interior and exterior protection for the fiber (PVC and galvanized tube)
Deployment of welder technicians to ensure more than 820 welds at the various junction points.
Assist the customer with all connection tests (1296 test to perform with zero failure).

Inspetores elétricos
IMG-20180820-WA0003.jpg
IMG-20181015-WA0010.jpg

HUAWEI / MOBILIS  -  Data Center of Bejaia

Site Survey and Design in BIM of the technical rooms and Building Facilities. 

Coordination of different infrastructures like cable tray, medium and low voltage, fiber optics, fire alarm, intrusion alarm, acces control, CCTV, humidity alarm, ventilation, AC and DC voltage with equipment installation and construction details.

Design of Dynamic 3D Viewing in BIMx for better site work implementation, coordination and control.

Task Planning and Quality Control.

As Build Drawings and Documents

WhatsApp%20Image%202018-12-16%20at%2017.
20181122 vuen 2.JPG
WhatsApp Image 2018-12-17 at 10.32.06.jp

HUAWEI / MOBILIS  -  Data Center of Annaba

Site Survey and Design in BIM of the technical rooms and Building Facilities, for an extension of the existant Data Center including one back up Exterior Container Data Center.

Coordination of different infrastructures like cable tray, medium and low voltage, fiber optics, fire alarm, intrusion alarm, acces control, CCTV, humidity alarm, ventilation, AC and DC voltage with equipment installation and construction details.

Design of Dynamic 3D Viewing in BIMx for better site work implementation, coordination and control.

Task Planning and Quality Control.

As Build Drawings and Documents

11.jpg
12.jpg

HUAWEI / MOBILIS  -  Data Center of Ouargla

Site Survey and Design in BIM of the technical rooms and Building Facilities.

Coordination of different infrastructures like cable tray, medium and low voltage, fiber optics, fire alarm, intrusion alarm, acces control, CCTV, humidity alarm, ventilation, AC and DC voltage with equipment installation and construction details.

Design of Dynamic 3D Viewing in BIMx for better site work implementation, coordination and control.

Task Planning and Quality Control.

As Build Drawings and Documents

Annotation 2020-02-01 193905.jpg
Annotation 2020-02-01 193558.jpg
Annotation 2020-02-01 193725.jpg
bottom of page